HC Deb 13 December 1982 vol 34 c47W
Mr. William Ross

asked the Secretary of State for Northern Ireland if he will list the various Northern Ireland river drainage schemes at present under way and indicate when they will be completed.

Mr. Adam Butler

The list of new works river drainage schemes presently underway and the years in which their projected completion is expected are as follows:

Scheme Projected year of completion
Holy well Bunn, Antrim 1983
Ahoghill Phase II 1983
Lynwood Park, Holy wood 1983
Pound Burn, Belfast 1983
Comber Road, Dundonald 1983
Ballyhay Burn, County Down 1983
Farset River Diversion, Belfast 1983
Manse Road, Newtownards 1984
River Main 1990

These dates may not be achieved if conditions are unfavourable, for example poor weather or difficulties in obtaining riparian agreements.