HC Deb 12 November 1980 vol 992 c254W
Mr. Bradford

asked the Secretary of State for Northern Ireland how many houses and flats are to be completed in the current phase of building at Pole-glass; and if the contract for the building of any of these dwellings now under construction was signed after the announcement of the freeze on public expenditure.

Mr. Goodhart

313 houses are included in the current phase of building. The contracts for these dwellings were let in November 1979, seven months before the announcement imposing a moratorium on new commitments.