HC Deb 10 November 1980 vol 992 cc29-30W
Mr. Harry Ewing

asked the Secretary of State for Scotland what was the number of vehicles using the A94 road north of Forfar in May; and what is the comparative figure for the month of May in each of the years since 1975.

Mr. Rifkind

The numbers of vehicles using the A94 trunk road north of Forfar in May each year since 1975 are as follows:

Year No. of vehicles per day
1975 4,549
1976 5,211
1977 4,435
1978 4,728
1979 5,057
1980 5,037

Mr. Ewing

asked the Secretary of State for Scotland what is the estimated completion date for the A94 dual carriageway construction north of Forfar; how many vehicles he expects to use the road as the time of completion; and what is the estimated capacity.

Mr. Rifkind

I expect dualled sections of the A94 trunk road north of Forfar to come into use from about 1983 on- wards. The timing of individual schemes will depend thereafter on availability of funds and the rate of progress on statutory and engineering preparation.

With a continued increase in North Sea oil developments and the transfer of traffic from the detrunked A92 coast road between Dundee and Stonehaven, it is expected that the present volume of traffic on the A94 will more than double by the 1990s. An A94 dual carriageway road will be capable of handling up to 30,000 vehicles per day.

Mr. Ewing

asked the Secretary of State for Scotland what is the present estimated cost of the construction of the proposed dual carriageway of the A94 to carry traffic north of Forfar.

Mr. Rifkind

£40 million at November 1979 prices.