HC Deb 15 May 1980 vol 984 cc568-73W
Mr. Roy Hughes

asked the Minister of Transport if he will list in the Official Report all motorway and trunk road schemes with a total cost of between £1 million and £10 million in the same format as the appendix on page VI-21 of the Supply Estimates 1980–81.

Mr. Kenneth Clarke

The information is attached for schemes in progress at 31 October 1979 and for those which have since started. As the hon. Member is aware, the whole programme has been under review. In the circumstances the provision referred to was not related to specific schemes in this range.

The total provision for schemes costing between £1 million and £10 million also covers expenditure on motorways communications, service areas and some other miscellaneous items and is partly off-set by the allowance at the end of table 2 of the appendix. The estimates for individual schemes are those current at

Estimated requirements for 1980–81
Year of athorisation to year of completion (estimated) Current estimate of total cost Probable expenditure to 31 March 1980 At 1980 survey prices At outturn prices
(1) (2) (3) (4) (5) (6)
£000 £000 £000 £000
MOTORWAYS
Schemes in progress (contracts let by 31 October 1979)
M25 Egham—Yeoveney (1.5 km) 1979–81 9,842 4,573 3,360 3,749
M25 Chersey—Wisley:
Advance Bridge Works, New Haw Viaduct, Wisley Interchange and Land 1979–81 11,552 2,301 3,813 4,255
Main Works Contracts 1 and 2 (9.4 km) 1981–83 28,266 825 159 177
Proposals to start (contracts actually let after 31 October 1979)
TRUNK ROADS
Schemes in progress (contracts let by 31 October 1979)
A10 Southery—South Runcton (16.1 km) 1977–80 5,469 4,210 778 868
Al Felton Bypass Main Works Stages 2A, B and C (4.7 km) 1978–81 4,462 1,602 1,790 1,997
Al GSJ at Darrington(l.6km) 1978–80 2,169 1,700 588 656
A259 Bexhill Old Town BP (1.4 km) 1978–80 3,031 2,136 440 491
A27 Portsbridge—Broad Marsh Improvement (3.2 km) 1979–80 2,572 1,503 1,192 1,330
A30 Billet Bridge—Avondale Road, Staines (1.6 km) 1979–81 1,440 339 575 642
A34 Whitchurch Litchfield Improvement (9.7 km) 1979–81 2,845 468 1,293 1,443
A406 Hangar Lane—Western Avenue (0.6 km) 1978–80 4,504 2,267 1,604 1,790
A47 Swaffham BP(7.6km) 1979–81 5,017 1,053 2,493 2,782
A52 Borrowash BP Extension (0.8 km) 1977–80 4,876 4,430 774 864
A590 Meathop—Sampool Bridge (6.2 km) 1979–82 8,223 1,686 3,059 3,413
A66 Appleby BP (6.4 km) 1978–81 9,028 3,642 3,642 4,063
A6 Silsoe BP (3 km) 1979–81 1,991 419 1,087 1,213
Proposals to start (contracts actually let after 31 October 1979)
A13 Newham Junction A13/117 (0.4 km) 1980–81 1,304 42 773 863
A31 Wimborne BP(5.8km) 1980–82 3,844 103 1,840 2,053
A590 Ulverston Diversion Stage 3 (1.0 km) 1980–81 1,227 68 667 744
A34 Kingsworthy—Bullington (9.3 km) 1980–82 8,322 45 3,267 3,645
Abbreviations:
BP—Bypass.
GSJ—Grade Separated Junction.
TABLE 1: DETAILS OF SCHEMES COSTING £1,000,000 OR MORE
Estimated requirements for 1980–81
Year of authorisation to year of completion (estimated) Current estimate of total cost Probable expenditure to 31 March 1980 At 1980 survey prices At outturn prices
(1) (2) (3) (4) (5) (6)
£000 £000 £000 £000
MOTORWAYS
Mhemes in progress (contracts let by 31 October 1979)
20 Mid—Kent Motorway:
Ashford to Folkestone (23 . 7 km) 1977–81 41,248 19,686 15,415 17,200
West Kingsdown to Addington (8 km) 1976–80 18,251 13,296 4,178 4,662

the time, and cover their total cost, including land and a contingency allowance. I have arranged for copies to be placed in the Library.

I regret that there is an error in three of the figures in the appendix to the Supply Estimates. A corrected version is attached and is available in the Library.

Estimated requirements for 1980–81
Year of authorisation to year of completion (estimated) Current estimate of total cost Probable expenditure to 31 March 1980 At 1980 survey prices At outturn prices
(1) (2) (3) (4) (5) (6)
£000 £000 £000 £000
M25 London Outer Orbital Motorway:
Thorpe to Chertsey (including Chertsey Links) (5.9 km) 1975–80 16,707 11,791 3,581 3,996
A12toA13(14.4km) 1978–82 62,213 12,604 20,358 22,716
A111 toA10(8.5km) 1979–81 21,989 6,978 10,654 11,888
M26 Sevenoaks—Wrotham Motorway:
Sevenoaks to Wrotham (12 km) 1977–80 22,089 15,665 5,374 5,996
M56 North Cheshire Motorway:
Hapsford to Lea by Backford (10.2 km) 1977–80 20,174 10,816 6,651 7,421
M58 Aintree—Skelmersdale M6 Motorway:
Aintree—Skelmersdale Link (13.2 km) 1977–80 32,186 24,892 5,679 6,337
M63 Manchester Outer Ring Road:
Stockport East/West By-Pass Stage 2 1978–81 11,144 3,060 3,149 3,514
M67 Hyde and Denton By-Pass Motorway:
Denton Relief Road, Stage 1 (2.4 km) 1978–81 18,816 12,053 4,469 4,987
Schemes with a total cost between £1,000,000 and £10,000,000 or requiring less than £2,000,000 in 198081 49,660 7,699 9,363 10,447
Residual expenditure on completed schemes costing £1,000,000 or more 27,584 30,779
Proposals to start (contracts let after 31 October 1979)
Ml London—Yorkshire Motorway:
Breakspears to Berrygrove (10.4 km) 1980–83 27,196 337 4,260 4,753
M25 London Outer Orbital Motorway:
Yeoveney to Poyle (including Airport Spur) (3.2 km) 1980–82 15,977 38 3,461 3,862
M11–A12(13.1 km) 1979–82 38,500 493 11,570 12,910
A10-M11 (12.9 km) 1979–82 83,114 3,574 11,494 12,825
M63 Manchester Outer Ring Road:
Stockport East/West By-Pass, Stages 4/5 (3.2 km) 1979–82 18,675 1,261 6,985 7,794
M65 Calder Valley Route:
Hyndburn to Burnley section (including Accrington Northerly By-Pass) 1980–82 45,115 2,176 4,642 5,180
Schemes with a total cost between £1,000,000 and £10,000,000 (contracts let after 31 October 1979) 3,000 3,000 3,317
Preliminary expenditure on land &c. for future schemes costing £1,000,000 or more 7,176 8,007
TOTAL 169,013 188,621
TRUNK ROADS
Schemes in progress (contracts let by 31 October 1979)
Manchester—Burnley Road:
Haslingdon By-Pass (4.2 km) 1978–81 15,861 3,184 5,883 6,564
Kendal—Doncaster Road:
Skipton Western and Northern By-Passes (North Yorkshire) (10.1 km) 1978–82 16,050 4,503 4,509 5,031
Penrith—Middlesbrough Road:
Stockton—Thornaby Diversion (Cleveland) (6.4 km) 1978–81 20,791 8,952 7,427 8,287
York—Hull Road:
Beverley South Western By-Pass (Humber—side) (10.0 km) 1978–80 11,253 5,344 4,484 5,003
Girton—Godmanchester Road:
Barhill to Godmanchester (Cambridge—shire) (19 km) 1978–81 12,799 4,890 4,149 4,630
London—Tilbury Road:
Mar Dyke—East of Grays (Essex) (9.9 km) 1979–81 25,724 4,465 11,466 12,794
London—Portsmouth Road:
Burpham to Ladymead Diversion (Hampshire) (6.3 km) 1977–81 17,430 10,906 5,631 6,283
Estimatea requirements for 1980–81
Year of authorisation to year of completion (estimated) Current estimate of total cost Probable-expenditure to 31 March 1980 At 1980 survey prices At outturn prices
(1) (2) (3) (4) (5) (6)
£000 £000 £000 £000
London—Holyhead Road:
Milton Keynes Diversion (Buckingham-shire) (15.3 km) 1977–80 21,378 18,828 3,537 3,947
London—Canterbury—Dover Road:
Canterbury By-Pass (Kent) (7.4 km) 1978–81 14,405 5,622 6,057 6,759
Felixstowe—Weedon and London—Yarmouth Roads:
Ipswich By-Pass (26.6 km) 1979–84 69,975 2,265 9,046 10,094
Schemes with a total cost between £1,000,000 and £10,000,000 or requiring less than £2,000,000 in 1980–81 61,626 25,455 24,903 27,787
Residual expenditure on completed schemes costing £1,000,000 or more 14,094 15,727
Proposals to start (contracts let after 31 October 1979)
East of Snaith—Sunderland Road:
Billingham Diversion (Cleveland) (7.4 km) 1979–82 16,138 2,969 4,671 5,212
Sheffield—Grimsby Road:
Brigg By-Pass to Grimsby (Humberside) (21.6 km) 1980–84 34,651 34 1,852 2,067
London-Fishguard Road:
Gloucester Northern By-Pass (5.3 km) 1980–83 10,550 1,521 878 980
Proposed Colchester-Harwich Road:
Colchester Eastern and Elmstead Market By-Pass (Essex) (13.2 km) 1979–82 20,903 1,374 7,119 7,944
Schemes with a total cost between £1,000,000 and £10,000,000 (contracts let after 31 October 1979) 65,122 786 16,265 18,149
Preliminary expenditure on land &c. for future schemes costing £1,000,000 or more 9,629 10,744
TOTAL 141,600 158,002
TABLE 2: SUMMARY AND RECONCILIATION WITH ESTIMATE
Current estimate of total cost Probable expenditure to 31 March 1980 Estimated requirements for 1980–81 at survey prices Estimated requirements for 1980–81 (at outturn prices)
£000 £000 £000 £000
MOTORWAYS AND TRUNK ROADS
Work in progress at 1 April 1980 on schemes costing more than £1,000,000 601,769 232,954 175,963 196,343
New schemes proposed to start in 1980–81 costing more than £1,000,000 379,031 14,563 76,197 85,023
Residual expenditure on completed schemes and preliminary expenditure on land, &c. for future schemes costing £1,000,000 or more 58,483 64,257
TOTAL 980,800 247,517 310,643 346,623
Other schemes costing less than £1,000,000 each 24,167 26,966
Less: Allowances for services which may not be carried out in the year 17,860 19,929
TOTAL 316,950 353,660