§ Mr. Dudley Smithasked the Minister of Transport what are the factors used to revalue 1979 survey prices to 1980 survey prices for trunk road construction, trunk road maintenance, local road construction and local road maintenance.
§ Mr. FowlerThe following factors have been used to revalue these programmes:
68W
1979 Survey Prices to 1980 Survey Prices Factors Motorway and trunk road Construction Roads Output Price Index 1.238 Land Cost Index 1.232
Factors Local Road Construction Tender Price Index 1.208 Cost Outturn Index 1.193 Land Cost Index 1.232 Motorway and trunk road Maintenance 1.193 Local Road Maintenance 1.174 Because the mix of expenditure between land, work in progress and new works varies from year to year, the overall effect of the revaluation can differ as between one year and another, even though the same underlying factors have been used.