§ Mr. Hoosonasked the Secretary of State for Wales whether the Government are satisfied with the rate of progress of work on the Brecon bypass; what was the original date of anticipated completion; and what is now expected to be the completion date.
§ Mr. Wyn RobertsYes. The original contract completion date was 16 April 1980. The completion date has since been extended to 20 May 1980, because of adverse weather. Given favourable conditions during the winter the bypass should be ready for opening in May.