§ Mr. Thomas Coxasked the Secretary of State for Social Services what is the 95W present position regarding the building of the new St. George's hospital, Tooting, London, S.W.17; and when this work will be completed.
§ Mr. Patrick Jenkin, pursuant to his reply [Official Report, 20 June 1979; Vol. 968, c. 599–600], gave the following answer:
Phase I
- Medical school pre-clinical departments and supporting facilities—In use.
- Medical school research facilities—To be completed by end of 1979.
- Hospital main entrance and office accommodation, school of nursing, lecture theatres—In use.
- Ward block of 270 acute beds—Building complete: Due for use in early 1980.
Phase II
- Medical school clinical accommodation and further research facilities—Work programmed to start 1980 and be completed 1982.
- Ward block of 340 acute beds—Work programme to start 1982 and be completed 1986.