HC Deb 15 June 1979 vol 968 c324W
Mr. Barry Jones

asked the Secretary of State for Wales how many advance factories have been constructed since the Deeside industrial park was started; how many square feet of factory space this represents; how many jobs now exist on Deeside industrial park and how many are estimated to be in the pipeline; how many advance factories not yet constructed are scheduled for Deeside industrial park; what is the estimated overall cost so far of developing the Deeside industrial park; and what is its current acreage.

Mr. Nicholas Edwards

Ten Government advance factories, totalling 78,000 sq. ft. have been completed. Seven are currently under construction with a total area of 75,000 sq. ft. A further 100,000 sq. ft. of advance factory space is scheduled for Alyn and Deeside district and a substantial proportion of this will be located on the Deeside industrial park. The total area of the park is 635 acres; planning approval for industrial development already exists for 360 acres. The Welsh Development Agency has acquired 55 acres of the site and has to date spent £1,431,795 on its development. Details of the development of the remainder of the park are a matter for British Steel Corporation (Industry) Ltd. A breakdown of male and female employment is not readily available. In total, 60 jobs are currently provided and an estimated 250 are in the pipeline.

Back to