HC Deb 22 May 1978 vol 950 c454W
Mr. Freud

asked the Secretary of State for Transport what is now the proposed date of opening of the Ely and Littleport bypass.

Mr. Horam

Subject to the satisfactory completion of the relevant statutory procedures and to the availability of funds at the time, we hope to start construction of this bypass in the period 1981–83, with completion two years later.