§ Mr. Bradfordasked the Secretary of State for Northern Ireland how many projects completed or under construction in Belfast under the Belfast areas of need programme overlap ward boundaries.
§ Mr. CarterThe two main projects initiated by the Belfast areas of need planning team which overlap ward boundaries are:
- (a) a general clean-up scheme extending to all BAN districts; and
- (b) a programme of renovation and redecoration for schools in BAN.
Work on both of those projects was undertaken during 1977–8 and will continue during1978–79.
§ Mr. Bradfordasked the Secretary of State for Northern Ireland if he will state the description, location and estimated cost of each project, outlined in the expenditure of the initial £2.6 million, which will be constructed within the South Belfast Imperial Constituency under the Belfast areas of need programme.
§ Mr. CarterThe following projects are funded from the initial £2.6 million being undertaken in that part of the South Belfast Imperial Constituency that is within the Belfast areas of need:
under the Belfast areas of need programme in Belfast to date.
§ Mr. CarterThis information is not readily available, but I shall arrange for it to be published in theOfficial Report at the earliest possible opportunity.