§ Lord James Douglas-Hamiltonasked the Secretary of State for Scotland if he will publish a table indicating the precise sums which may be gained or lost by each region in Scotland in rate support grant, as a result of the assessor's revaluation of rateable property in Scotland.
§ Mr. MillanPrecise calculation of the effects of revaluation alone on the distribution of rate support grant could only be undertaken at disproportionate cost.
100W
A96 Huntly Bypass 1.63 A882 Burnside-Scrabster 0.63 A830 Annat-Drumsallie 1.68 Estimated completions in 1979 A1 Henderson's Bridge 1.46 A9 Calvine-Regional Boundary 14.59 A9 Crubenmore-North of Kin-gussie 5.85 A9 Avielochan-Slochd 7.53 A83 Fyne Bridge 0.60 A96 Woodside-Colpy 0.59 A76 Auldgirth Diversion 0.96 M876 North Broomage-Bowtrees 10.41 Estimated completions in 1980 M8 Baillieston Interchange 8.87 M90 Arngask-Muirmont 8.40 A972 Kingsway, Dundee Phase I 3.71
§ Lord James Douglas-Hamiltonasked the Secretary of State for Scotland, which trunk roads and motorways are planned throughout Scotland in the near future; and what is their estimated cost.
§ Mr. McElhoneTrunk road and motorway schemes costing over £500,000 which it is hoped to start in the period up to 31st March 1980 are as shown in the following table:
Full information necessary for this calculation is in any event not yet available.