HC Deb 02 March 1978 vol 945 c377W
Mr. Michael McNair-Wilson

asked the Secretary of State for Defence what work is being carried out on the runways and other facilities at RAF Greenham; and if he will give details of the contracts relating to this work including how much is being spent and when the work is expected to be finished.

Mr. Wellbeloved

As I explained to the hon. Member in my letter of 10th October 1977, the runway and taxiways at RAF Greenham Common are currently being resurfaced. The work is being carried out at a cost of about £700,000. The work is due for completion by the end of April 1978. The resurfacing of the runway is part of the normal maintenance programme to ensure that the airfield is in the best condition to meet its existing standby commitment. No other work of any significance is being carried out at present.

Forward to