HC Deb 30 June 1978 vol 952 cc713-4W
Mr. Molloy

asked the Secretary of State for Transport what progress, following the conference initiated by him which included representatives of the Greater London Council, the London borough of Ealing, police, local residents, and the hon. Member for Ealing, North, has been made on construction work for the A40 at Greenford roundabout, Middlesex in relation to improving pedestrian safety.

Mr. Horam

The measures agreed at the meeting on 16th June have been implemented with the exception of improved surfacing of temporary footpaths, which is almost complete, provision of a spare traffic signal controller and a traffic signal ahead sign.

The controller and sign have been ordered and should be provided within three weeks.

Forward to