HC Deb 19 June 1978 vol 952 c62W
Mr. Powell

asked the Secretary of State for Northern Ireland what is the estimated cost at current prices of completing the Banbridge eastern bypass (a) double carriageways throughout now, (b) single carriageways now, and (c) the remaining carriageways subsequently.

Mr. Carter

The estimated costs are £3,225,000, £2,700,000—to include a section of dual carriageway at each end—and £585,000 respectively.