HC Deb 23 January 1978 vol 942 cc482-3W
Mr. Molloy

asked the Secretary of State for Social Services what progress has been made regarding completion of the new Ealing Hospital; and if he will make a statement.

Mr. Moyle

The main ward tower became available during December. I understand that the contractors expect the west podium and its associated tower floors to be available by 31st January 1978. Completion of the east podium is expected by end of March 1978. It is intended that the area commissioning team should start taking over the building six weeks before estimated final date for completion.