HC Deb 21 February 1978 vol 944 c573W
Mr. Buchanan-Smith

asked the Secretary of State for Scotland when he expects to place a contract for the completion of the Aberdeen—Commachmore A92 dual carriageway; when he expects work to start; and when he expects the contract to be completed.

Mr. McElhone

The selection of contractors to be invited to tender for this scheme is at present in hand. I hope that the contract will be placed this summer, with a start on site soon thereafter and completion late in 1980.