§ Mr. Rookerasked the Secretary of State for Transport how the present traffic flow on the M6 motorway in the West Midlands county compares with predictions made at the design stage.
§ Mr. HoramPredicted and observed flows on the M6 are as follows:
Predicted Observed (West of M5 Junction) 76,000 88,000 (East of M5 Junction) 78,000 67,000 Figures are average two-way traffic flows per 16-hour day.
§ Mr. Rookerasked the Secretary of State for Transport how many cross beam bearings there are on the elevated sections of the M6 motorway in the West Midlands county; how many have recently been inspected and found defective; and what is the estimated cost of replacement.
§ Mr. HoramThere are 13,274 cross beam bearings on the M6 motorway in the West Midlands county. Since 1975