HC Deb 02 March 1977 vol 927 c255W
Mr. Rippon

asked the Secretary of State for Transport what progress has been made towards the completion of the strategic network of 3,500 miles of first-

Amendments Estimated start On 4,500-mile Network
Scheme
A13 Lodge Lane Improvement (f)
A41 Whitchurch Bypass (f) *
A46 Newark Relief Road (c) *
A52 Borowash Bypass Extension (b) *
A590 Dalton in Furness Bypass (c) *
Additions
M25 Enfield D Ring A111-A10 (a) *
M65 M6/M6I Whitebirk (b) *
A10 Brandon Creek-Southery (f) *
A27 Lewes to Beddingham (c) *
A41 Whitchurch to M54 (f) *
A46 Coventry Bypass (f) *
A47 Leicester to A1 (f) *
A49 Ross on Wye Bypass (f) *
A419 Groundwell Corner (f) *
A419 Latton Bypass (f) *
A458 A5 to Welsh Border (f) *
A606 Improvement at Tollerton (f) *
A5117/A550 Junction (f) *
Lincoln Relief Road (f) *
Leicester Western Bypass (f) *
A1(M) Eastwards to A66 (f)
Ringway 3 M4-Uxbridge Road (f)
Ringway 3 MI-A4020 (f)
The possible start date of schemes depends on many factors, including engineering design, statutory procedures, and availability of resources. Any start dates given must, therefore, be taken as subject to change. They will he advanced wherever circumstances permit.
They are quoted in bands:
(a) 1977.
(b) 1978 and 1979.
(c) 1980–82.
(d) 1983–85.
(e) After 1985.
(f) No start date determined.
The schemes on roads included in the 4,500 mile strategic network are marked *.