HC Deb 15 December 1977 vol 941 c317W
Mr. Hooley

asked the Secretary of State for Energy what is the most recent estimate of the capital cost of a 600 MW fast breeder reactor at 1977 prices; and how this compares with earlier estimates in real terms.

Mr. Eadie

To provide adequate demonstration on a commercial scale, design work on a commercial demonstration fast reactor is concentrated on a

£ million
(estimated)
1973–74 1974–75 1975–76 1976–77 1977–78
British Nuclear Fules Ltd. 5.3 9.9 23.9 26.0 49
UK Atomic Energy Authority 0.2 0.4 1.4 1.9 0.5
URENCO 1 12 17 13