§ Mr. Nicholas Wintertonasked the Secretary of State for Education and Science what was the total cost of (a) all secondary and school building projects, (b) all primary and infant school building projects and (c) other educational building projects completed in each of the last five 448W years in the area covered by the Macclesfield constituency.
§ Miss Margaret JacksonThe Department does not maintain records of school building projects by reference to parliamentary constituencies, but I am informed by the Cheshire Education Authority that the tender prices of major building projects started were as follows:
Primary Secondary Nursery and Special Education 1972–73 … 421,767 116,000 — 1973–74 … 222,123 — 62,578 1974–75 … 176,471 768,350 237,579 1975–76 … 167,552 335,158 37,480 1976–77 … — 541,730 —