§ 35. Mr. Brothertonasked the Secretary of State for Transport what is the latest estimate of the cost of the Humber Bridge.
§ Mr. HoramThe Humber Bridge Board recently announced that the cost of the bridge, including its immediate approach roads, is now estimated to be £54 million at August 1976 prices.
§ 53. Mr. John Ellisasked the Secretary of State for Transport what is the latest estimate of the cost of the Humber Bridge; and when it will be completed.
§ Mr. HoramThe Humber Bridge Board recently announced that the cost of the bridge, including its immediate approach roads, is now estimated to be £54 million at August 1976 prices, and the anticipated opening date is now March 1979.