§ Mr. Hayhoeasked the Secretary of State for Energy what was the original estimated cost, and the current estimated 419W cost both at actual and constant prices, of each of the CEGB nuclear power stations currently under construction.
§ Mr. EadieThe CEGB has four nuclear power stations currently under
£ Million Dungeness "B" Hinkley Point "B" Hartlepoot Heysham Date of original estimate 31st March 1965 31st March 1966 31st October 1968 30th November 1970 Original estimate at prices at dates given above 89 95 92 142 Current estimated actual costs (i.e. at prices as actually paid or anticipated to be paid in future) 280 140 220 240 Current estimated costs at constant prices ruling at date(s) of original estimates 186 126 158 174