HC Deb 07 July 1975 vol 895 c49W
Mr. Wigley

asked the Secretary of State for Scotland if he will list in the Official Report the names, date of start and date of completion, where appropriate, of all power stations constructed or under construction since 1960 by the SSEB.

Mr. William Ross

The names, date of start and date of completion, where appropriate, of the South of Scotland Electricity Board power stations in question are listed below:

Name of Station Start on site Date of completion
Conventional Steam Stations
Kincardine 1955 1963
Cockenzie 1962 1968
Methil 1962 1966
Longannet 1964 1971
Inverkip 1970 Not yet completed
Nuclear Stations
Hunterston "A" 1957 1964
Hunterston "B" 1967 Not yet completed
Main Gas Turbines
Clyde's Mill 1963 1965
Dunfermline 1963 1965