HC Deb 04 August 1975 vol 897 c65W
Mr. Fairbairn

asked the Secretary of State for the Environment if he will list the detailed costs of the work proceeding in New Palace Yard, broken down into items; and whether there is any increase in these costs over the price agreed.

Mr. Armstrong

The latest total order of cost for the work is £291,500. £54,500 of this was spent on Phase I, which comprised preparation of the central area to enable the early planting of trees. £16,500 of the Phase I cost was spent on work carried out by the Bailiff of the Royal Parks. The estimated cost of work on Phase II, which is not yet complete, is £237,000. This will involve paving the roadway with granite setts, providing a paved footpath, with granite scats, and installing a new entrance porch. There has been a very slight increase on the original estimated cost of Phase I.