HC Deb 17 April 1975 vol 890 c168W
Sir Raymond Gower

asked the Secretary of State for Wales if he will list, giving the estimated cost of each, those trunk and principal road schemes, costing over £250,000, which were added to the forward road programme during the six months ended 31st March 1975.

Mr. John Morris

No trunk road schemes were added to the firm programme during the six months ended 31st March 1975. The information in respect of principal roads is as follows:

Scheme Estimated Cost
A4086 Llanberis to Nantperis (County of Gwynedd). £250,000

Sir Raymond Gower

asked the Secretary of State for Wales what was the total value of trunk and principal roads, respectively, firmly programmed as at 31st March 1975.

Mr. John Morris

The information is as follows:

Motorways and Trunk Roads £137.6 million
Principal Roads £24.2 million