HC Deb 11 November 1974 vol 881 c41W
Mr. Crouch

asked the Secretary of State for the Environment if he will make a statement regarding the progress of work on the improvements to the A2

Section Progress Estimated completion
Boughton and Dunkirk bypass Under construction Winter 1975
Harbledowns bypass Contract let and construction to begin shortly. Spring 1976
Canterbury bypass Consultants appointed for design of scheme. Programming dates not yet determined
Preparation work proceeding.
Bridge bypass Under construction Summer 1976
Bishopbourne Road to Black Robin Lane Under construction Summer 1976
Barham Crossroads to Ropersole Farm Work completed Now open
Lydden to Dover diversion Contract let for first (⅓ mile) section at Dover. Summer 1976
Contract for remaining section expected to be let at turn of this year.