HC Deb 29 July 1974 vol 878 cc92-3W
Mr. Kilfedder

asked the Secretary of State for Northern Ireland what was the total cost of the gymnasium, the erection of separate accommodation for special grade boys, the erection of a boiler house, the provision of a new boiler, an extension to the kitchens and the construction of staff garages, respectively, at the borstal, Millisle.

Mr. Merlyn Rees

The erection of the gymnasium and the extension to the kitchens at Her Majesty's Borstal, Millisle, were part of a general programme of construction work started in 1957, which finally cost £58,000. A breakdown of this sum between the various projects is not readily available.

The costs of the other projects were:

£
Boilerhouse, boiler and associated works 20,290
Special grade accommodation 16,800
Staff garages 9,800