HC Deb 16 December 1974 vol 883 cc361-2W
Mr. Geraint Howells

asked the Secretary of State for Wales what is the total payment in Dyfed under the need resources elements of rate support grant in 1974–75; and if he will estimate the amount for 1975–76.

Mr. John Morris

Under the first Rate Support Grant Order for 1974–75 the amount of needs element grant for Dyfed for that year was about £15 million and the amount of resources element grant about £12.3 million, a total of £27.3 million. Taking into account the increase order the amounts payable will be about £20.8 million and £13.8 million respectively, a total of £34.6 million. The first estimate of the amount of needs element grant in 1975–76 is about £20.7 million. The amount of resources element grant for each local authority in 1975–76 will depend upon the level of expenditure of that authority.

Mr. Geraint Howells

asked the Secretary of State for Wales how much rate support grant will be paid in Dyfed under the sparsity and super-sparsity factors in 1974–75; and if he will estimate the amount for 1975–76.

Mr. John Morris

Under the first Rate Support Grant Order for 1974–75 the amount of grant to be paid in Dyfed in that year on account of sparsity of population was about £4.45 million. Taking into account the increase order the amount payable will be approximately £6.2 million. The first estimate of the amount payable for 1975–76 is about £4.60 million.