HC Deb 16 October 1973 vol 861 c142W
Mr. Rowlands

asked the Secretary of State for Wales what is the estimated date of completion of each of the stages of the Cardiff-Merthyr trunk road; and when he now expects construction to begin on the Abercynon/Cefn Coed sections of that road.

Mr. Peter Thomas

I expect the section between Upper Boat and Abercynon to be opened about the end of November. It is too early to forecast starting dates for the remaining stages.