HC Deb 14 November 1973 vol 864 cc167-8W
Mr. Warren

asked the Secretary of State for Trade and Industry what is the power output to the national grid scheduled to be delivered from nuclear power plants this year and in each of the succeeding four years, listing the power stations and types of reactor involved.

Mr. Emery

The output of the existing nuclear power plants at 31st March 1973 was as follows:

Station Maximum Output Capacity MW s.o. Type of Reactor Operator
Bradwell 250 Magnox CEGB
Dungeness A 410 Magnox CEGB
Sizewell A 420 Magnox CEGB
Hinkley Point A 460 Magnox CEGB
Oldbury on Severn 400 Magnox CEGB
Berkeley 276 Magnox CEGB
Trawsfyndd 390 Magnox CEGB
Wylfa 840 Magnox CEGB
Hunterston A 300 Magnox SSEB
Chapelcross 198 Magnox BNFL
Calder Hall 198 Magnox BNFL
Windscale 34 AGR UKEA
Winfrith 100 SGHWR UKEA
Dounreay Experimental Reactor 14 Fast Breeder UKEA

No further nuclear plant is scheduled to come into service this year.

I am asking the Chairman of the CEGB to send my hon. Friend such information as may be available about planned nuclear capacity over the succeeding four years. My right hon. Friend the Secretary of State for Scotland will also ask the Chairman of the SSEB to write to my hon. Friend. I am advised by the UKAEA that the 250-MW prototype fast reactor at Dounreay should start to generate electricity next year.