HC Deb 23 July 1973 vol 860 c321W
Mr. Eadie

asked the Secretary of State for Scotland what advice he has received regarding the operation of Inverkip Power Station; and how many megawatts will be produced in 1975, 1976 and 1977.

Mr. Gordon Campbell

The output capacity of Inverkip is planned to reach 630 MW in 1975; 1,260 MW in 1976; 1,890 MW in 1977.