HC Deb 22 June 1972 vol 839 c182W
Mr. Barry Jones

asked the Secretary of State for Wales if he will list the primary schools currently under construction in the East Flintshire constituency; what are the proposed opening dates and their respective estimated costs; and how many will have nursery class departments.

Mr. Peter Thomas

The Welsh Office collects information about schools and school buildings by reference to complete local education authority areas, not parliamentary constituencies. I am however informed by the local education Authority that within the East Flintshire constituency a new infants' school at Buckley is under construction and work will start soon on a new infants' school at Hawarden and on extensions to a junior school at Connah's Quay. The estimated costs of these projects are £42,281, £87,438 and £46,241 and the estimated opening dates are April, September and January, 1973, respectively. It is not proposed to attach nursery classes to these three schools.