asked the Secretary of State for the environment if he will give the total value of trunk and principal road schemes, respectively, firmly programmed.

Mr. Speed

The total value of major road schemes in the firm roads programme as at 1st July, 1972, is as follows:

£ million
Trunk roads (including motorways) 615
Principal roads 551

Mr. Redmond

asked the Secretary of State for the Environment if he will list those trunk and principal road schemes, giving the estimated cost of each which were added to the forward programme during the six months ended 31st March, last.

Mr. Speed

I have nothing to add to the answer I gave my hon. Friend on 18th April last.—[Vol. 835, c.72–4.]