§ Sir R. Russellasked the Secretary of State for the Environment when the improvement works on the Hogarth roundabout on the A4 at Chiswick were begun ; what is the anticipated date of completion ; and what has delayed progress on this work.
§ Mr. Graham PageWork started in January and I expect it to be completed by early autumn. There has been some delay in the delivery of signal equipment. In addition, the work has had to be arranged so as to minimise disruption of traffic at this very busy junction.