HC Deb 08 December 1971 vol 827 cc309-10W
Mr. Redmond

asked the Secretary of State for the Environment if he will list those feasibility studies for road schemes in respect of which he has not yet made a decision, giving in each case the date when the study was commissioned and, where appropriate, the date the result of the study was received by him.

Mr. Michael Heseltine

The situation on the major feasibility studies is as follows:

  • South of Leeds to North-East—the corn-mission was placed in October, 1968 and the Final Report was received in August, 1970—some further work has been commissioned.
  • Strensham-Solihull—the commission was placed in May, 1968 and an interim report received in April, 1970.
  • Oxford-Birmingham—the commission was placed in May, 1968 and a series of reports have been submitted up to recent months. Further studies are proceeding.
  • Ringway 3 South—the commission was placed in August, 1969 and the study is continuing.
  • Sheffield-Manchester—the commission was placed in November, 1968 and a Final Report received in March, 1970.
  • North Devon Link—the commission was placed in July, 1970 and the Final Report has lust been received.
  • A.3 Peterstield-Guildford—the commission was placed in July, 1968 and the Final Report received in June, 1971.
  • Chichester to East of Worthing—the commission was placed in April, 1967 and the Final Report received in March, 1971.
On those studies where Reports have been submitted, further work and consultation will be necessary before firm proposals can be announced.