§ Mr. Michael Cocksasked the Secretary of State for Social Services what was the original estimate of the cost of the new Bristol Royal Infirmary Radiotherapy Centre; what was the original estimate of the on site costs of this project; what was the actual cost of the new Bristol Royal Infirmary Radiotherapy Centre; and what were the actual on site costs of the new Bristol Royal Infirmary Radiotherapy Centre.
§ Mr. AlisonThe original estimate of cost prior to tender in 1966 was £1,441,000, comprising £969,000 for building and engineering work and £472,000 for fees and equipment.
The contract final account has not yet been agreed; the latest estimate is £1,713,000, comprising £1,092,000 for building and engineering and £621,000 for fees and equipment.