HC Deb 20 November 1970 vol 806 cc508-9W
Dr. David Owen

asked the Secretary of State for the Environment what major roadworks between now and the end of 1975 he plans to construct in the South-West development area.

Mr. Michael Heseltine

The following trunk road schemes are programmed to start in 1972:

  • A30—Camborne and Scorrier Bypass.
  • A38—Liskeard Bypass.

The following major trunk road schemes are also in preparation and may be completed or under construction by the end of 1975:

  • A30—Chyandour-Polstrong improvement.
  • A30—Launceston Bypass.
  • A30-A38—Bodmin Bypass.
  • A38—Tinkerslake improvement.
  • A38—Trethawle improvement.
  • A39—St. Columb Bypass.
  • A39-A361—Barnstaple Bridge and Bypass.

Target years for start of works of these schemes will be determined at a later stage of planning.