§ 60. Mr. Brooksasked the Secretary of State for Defence whether he will publish in the OFFICIAL REPORT a list of the Polaris and Fleet submarines which have either been constructed, or are in process of completion, in British shipyards; and whether he will indicate the final cost of those completed, or the latest estimated cost of those under construction, in each case.
§ Mr. John Morris:A list of Polaris submarines which have been accepted into H.M. Service with figures of final or estimated final cost is as follows:
£ million " Resolution " 40. 2 " Renown " 39. 5 " Repulse " 37. 5 " Revenge " 38. 6 For Fleet submarines, the list is as follows:
£ million " Dreadnought" 18. 5 " Valiant" 24. 9 " Warspite " 21. 5 The following Fleet submarines have not yet been accepted into H.M. Service, 288W and for this reason it is not the practice, on commercial grounds, to publish their final estimated cost:
- "Churchill".
- "Conqueror".
- "Courageous".
- "Swiftsure".
- "SSN 08".