HC Deb 19 February 1970 vol 796 c190W
Mr. Judd

asked the Minister of Public Building and Works what was the approved estimated cost of construction for the Central Office Block Number One in Portsmouth Dockyard; what was the actual final cost; what has been the total cost of modifications, repairs and improvements since completion; and whether he will make a statement.

Mr. John Silkin

In March, 1963 when construction started Central Office Block Number One was estimated to cost £331,000. My Department spent £358,000 on this building together with a further £16,000 after occupation had taken place.