§ Mr. Hastingsasked the Minister of Public Building and Works (1) what was the final cost of the computer block and office block, respectively, showing separately the cost of the land at the Schedule E computer centre at East Kilbride;
(2) what were the dates on which contracts were let for the computer block and office block for the Schedule E computer centre at East Kilbride, and the dates on which these were handed over to the Inland Revenue.
§ Mr. John SilkinIt is not possible to identify separately the cost of the two
Bootle Cardiff Main Contract Let 22nd November 1968 2nd January 1970 Main Contract Starting Date 30th December 1968 Expected to follow completion of present piling contract. Contract Completion Dates Computer (ADP) Accommodation 30th September 1970 early 1972. Remainder 31st December 1970 early 1972. Estimated Cost Buildings £4,900,000 £4,950,000. Sites £320,000 Existing Crown Freehold site. The A.D.P. accommodation is an integral part of the office block and its cost cannot be precisely separated. At Bootle, progress on site has been delayed by difficulties which could not have been foreseen; the timetable is under review. At Cardiff it is hoped to meet the present completion date.
§ Mr. Hastingsasked the Minister of Public Building and Works what are the
88W
Invite Tenders Place main Contract (provisional) Provisional Contract Completion Dates Shipley … … … mid-1970 end-1970 ADP Accommodation mid-1973 Rest, end-1973 Rest, end-1973 Manchester … … … Autumn 1970 early 1971 ADP Accommodation end-1973 Rest, Autumn 1974 Washington … … … Planning now starting Not yet assessed Edinburgh … … Not yet in planning. Portsmouth … … Midlands … … blocks. The latest estimate of the total cost of the project in advance of the settlement of the final account is £2.16 million. The land is held on feu at a rate of £2,890 per annum. The main contract for the whole project was let on 25th August, 1965 and it was handed over to the Inland Revenue in stages between October, 1967 and November, 1968.
§ Mr. Hastingsasked the Minister of Public Building and Works (1) what were the dates on which the contracts were let for the computer block and office block at the Schedule E computer centres at Bootle and Cardiff, respectively, the dates on which the contracts specified these buildings were to be completed, and the dates on which he now estimates that each of these blocks will be completed;
(2) what is the estimated cost of the computer block and office block, respectively, showing separately the cost of the land, at each of the Schedule E computer centres at Bootle and Cardiff.
§ Mr. John SilkinThe information is as follows:
dates on which he will go out to tender for, place contracts for, and have completed, the office and computer blocks for each of the Schedule E computer centres at Shipley, Manchester, Harlington, Edinburgh, Portsmouth, and in the Midlands.
§ Mr. John SilkinThe following is the information: