HC Deb 20 October 1969 vol 788 cc169-70W
Mr. Eadie

asked the Secretary of State for Scotland when he expects the Longannet coal-fired power station to be in operation; when he expects the Hunterston B nuclear station to be in operation; and what he estimates will be the cost per unit sent out from each.

Mr. Ross

Generation of electricity is expected to start at Longannet about the end of this year and from Hunterston B early in 1973. On the basis of a 30-year life with interest at 8 per cent. the South of Scotland Electricity Board estimate that the cost of electricity to be sent out from Longannet will be 0.60d. per unit. I gave the estimated cost of electricity to be sent out from Hunterston B in reply to my hon. Friend on 1st April, 1969.—[Vol. 781, c. 79–80.]