HC Deb 17 July 1969 vol 787 c198W
Mr. E. Rowlands

asked the Secretary of State for Wales, in view of the evidence of the Cardiff City Engineer that the proposed Llantrisant radial road is dependent on the proposed Cardiff hook road being finished by 1976, to what extent his plans to build the Llantrisant radial road are dependent on progress with the Cardiff hook road.

Mr. George Thomas

The trunk route of which the Llantrisant radial road will be a part will need to serve traffic to and from Cardiff as well as through traffic, but its building will not be dependent upon progress with any particular scheme of internal road improvements.