HC Deb 22 January 1969 vol 776 c111W
Mr. Albu

asked the Minister of Technology on what date the development of the Blue Streak missile was commenced; what was the original estimate of its cost; and what was the amount of money expended at its cancellation.

Mr. J. P. W. Mallalieu

The first contracts with industry to develop Blue Streak were placed in November, 1955, and the estimate for a 10-year period of work was £50.75 million. £65 million had been expended to April, 1960, when the project was cancelled and a further £19 million rundown costs were incurred making a total of £84 million.