asked the Minister of Public Building and Works now dampness occurred on the internal walls of bedrooms on the lower floors of numbers 7 to 10 and 42 to 56 Wylye Road, Tidworth, in view of the fact that these houses were constructed with a vertical damp-proof course.

Mr. Mellish

Tests indicate that the dampness is consistent with residual building moisture. The normal drying-out process is more prolonged than usual in these walls because the damp-proof course prevents drying-out towards the exterior and the rooms face north. Some condensation may also have occurred because the walls were cold.

Mr. Charles Morrison

asked the Minister of Public Building and Works if he will list the main items of expenditure with individual costs which together have caused an average expenditure of £233 since completion on numbers 7 to 10 and 42 to 56 Wylye Road, Tidworth.

Mr. Mellish

The main items of expenditure per house were:

£
Lining back wall of 2 bedrooms with match-boarding 63
Boarding up windows on vacation to prevent vandalism 22
Installing off-peak electric heaters on lower floor 43
Repairs to glazing 15
Internal redecoration 70
Minor works 20