HC Deb 04 July 1968 vol 767 c270W
Mr. Carlisle

asked the Minister of Transport (1) what is the present position with regard to the scheme for widening the existing A56 road through part of the village of Helsby which was commenced at Whitsuntide 1966;

(2) what is the current estimate of the total cost involved in the present scheme for widening the A56 road through part of the village of Helsby on which work commenced at Whitsuntide 1966.

Mr. Bob Brown

This scheme is completed except for final surfacing and the provision of an island. The current estimated cost is about £41,000.

Forward to