HC Deb 07 March 1967 vol 742 cc233-4W
45. Mr. Bruce-Gardyne

asked the Chancellor of the Exchequer what estimate he has made of the shortfall in fulfilment of the current agreement on support costs for the Rhine Army to 31st March, 1967, before allowance is made for any advance payments on account of equipment to be procured subsequently.

Mr. Callaghan

The obligation accepted by the Federal German Republic is to make payments which count for the purposes of Articles 2(a) and (b) of the Agreement of the 27th July, 1964, amounting, in the year 1966–67, to approximately DM600 million. I anticipate that by 31st March, 1967, procurement and payments will exceed this figure. Deliveries will not be completed until after the 31st March, 1967.