HC Deb 26 June 1967 vol 749 c21W
Mr. Eldon Griffiths

asked the Minister of Public Building and Works on how many occasions during the present session repair work has been carried out on the lift at No. 1 Bridge Street; how many man-hours have been devoted to this task; and what is the approximate cost of the labour and materials involved.

Mr. Prentice

Minor repairs and adjustments have been carried out on 19 occasions during the present session. The work has occupied about 108 man hours at a cost, including materials, of about £125. I am aware of the shortcomings of this lift but the only way of improving the facilities would be by installing a completely new lift. Not only would this cost nearly £10,000 but it would also take 18 months and cause considerable inconvenience, including interruption of the lift service, while in progress. As No. 1 Bridge Street is in any case due to be demolished within the next few years, I should not be justified in undertaking this work.