HC Deb 06 December 1967 vol 755 c296W
46. Mr. G. Campbell

asked the Secretary of State for Scotland if he will make a statement on progress with the power station at Longannet.

Dr. Dickson Mabon

The South of Scotland Electricity Board expects that the first two 600 MW sets will be completed in 1969, and that the station will be fully commissioned during 1971 as planned.