§ Mr. Channonasked the Chancellor of the Exchequer how many contracts for building and civil engineering works which have an estimated completion date of May 1968 or later in the United Kingdom his Department entered into before 3rd May 1966 with a standard form of contract without a variation clause; and what is the total value of the contracts.
§ Mr. DiamondNone.
§ Mr. Channonasked the Chancellor of the Exchequer how many contracts for building and civil engineering works in the United Kingdom which have an estimated completion date of between May 1967 and May 1968 his Department entered into before 3rd May 1966 with a standard form of contract without a variation clause; and what is the total value of the contracts.
§ Mr. DiamondNone.