§ Mr. Donald Andersonasked the Secretary of State for Wales whether 31st August, the original expected completion date of the Crick-Coldra section of the M4 motorway, still stands.
§ Mr. Cledwyn HughesThe original contract completion date was 6th July, 1966. Under the terms of contract the contractor is entitled to certain extensions of time and these have been allowed by the consulting engineers responsible for the supervision of the contract on350W my behalf. The contract completion date is now 31st August, 1966, but there is some doubt whether this date will be met and the situation is being urgently reviewed.